  • Two frameworks coexist: ① law 82-21 (self-production) — in principle self-consumption, with surplus injection capped at 20% of annual production; ② law 13-09 (amended by law 40-19, independent producer) — the operator may supply a consumer or a group of consumers connected to the national grid, and the distribution system operator.
  • Official wording (ANRE 2025 annual report): law 13-09 allows commercialisation of renewable electricity to consumers or groups of consumers, so the direct corporate PPA route is established.
  • The surplus cap is identical under both frameworks (at most 20% of annual production); THT/HT injection to ONEE, MT injection to the distributor.
  • Commercial terms are not a matter of legal fact: duration, price, guarantees, network tariffs (TURT/TSS/TURD) and registration require written guidance from the ANRE or the ministry, or legal advice.
  • See also the record on green electricity purchase and sale routes (from 1 March 2026: TURT 6.85 / TSS 6.81 / TURD 6.07 cDH/kWh).

Official sources

Facts in this record rely on an official primary source; texts may be amended, so refer to the official text and the latest Bulletin Officiel.

Need hands-on support (procedures, documents, dedicated follow-up)? View services · Contact us

#policy-ppa-structures

Apply