Morocco: legal framework for power plants — Laws 13-09 / 82-21 and grid-connection approval

In force

Effective date
Per the official text
Verification date
2026-08-12
Source
Official primary source (see link below)
  • Law 13-09 governs renewable electricity production; Law 82-21 governs self-production of electricity.
  • The electricity regulator (ANRE) issues and publishes the decisions framing grid access and tariffs; approval of grid connection remains with the system operators.
  • Relevant technical reference: ANRE CRENT (grid-connection technical requirements) — frequency 47–52 Hz; transmission voltage 0.9–1.15 pu; THD ≤ 3%.
  • Official source: ANRE (https://anre.ma), including the official Bulletin Officiel text of Law 82-21 (BO 7400).

Official sources

Facts in this record rely on an official primary source; texts may be amended, so refer to the official text and the latest Bulletin Officiel.

Need hands-on support (procedures, documents, dedicated follow-up)? View services · Contact us

#39baca3f-345e-4d8c-9796-7a40656f159c

Apply