Morocco: legal framework for power plants — Laws 13-09 / 82-21 and grid-connection approval
In force
- Effective date
- Per the official text
- Verification date
- 2026-08-12
- Source
- Official primary source (see link below)
- Law 13-09 governs renewable electricity production; Law 82-21 governs self-production of electricity.
- The electricity regulator (ANRE) issues and publishes the decisions framing grid access and tariffs; approval of grid connection remains with the system operators.
- Relevant technical reference: ANRE CRENT (grid-connection technical requirements) — frequency 47–52 Hz; transmission voltage 0.9–1.15 pu; THD ≤ 3%.
- Official source: ANRE (https://anre.ma), including the official Bulletin Officiel text of Law 82-21 (BO 7400).