Self-generation of electricity and grid connection (law 82-21)
In force
- Effective date
- Per the official text
- Verification date
- 2026-09-24
- Source
- Official primary source (see link below)
- Legal basis: law 82-21 (self-production), published in BO no. 7400; implementing decree 2-25-100.
- Paliers by capacity and connection mode: off-grid declaration; low-voltage registration; medium-voltage (< 5 MW) connection agreement; above (≥ 5 MW) authorisation.
- Surplus: injection of surplus is limited to 20% of annual production; remuneration follows the ANRE decision (MAD 0.18–0.21/kWh).
- Procedure: grid impact study → technical review → signature of the connection agreement; works must be completed within 2 years of signature.
- Capacity: verify the hosting capacity of the target node with ONEE/SRM beforehand.
Official sources
Facts in this record rely on an official primary source; texts may be amended, so refer to the official text and the latest Bulletin Officiel.
Need hands-on support (procedures, documents, dedicated follow-up)? View services · Contact us
#policy-self-generation-grid